Spring Brings Construction Progress - April 2017

Spring Brings Construction Progress - April 2017

IMPORTANT TRAFFIC INFO: 20th Ave and 5th Street closed April 20-22. 

Click here for April 20 traffic map.  Click here for April 21 traffic Map.

 

Construction on our medical office building has come a long way in five months! As of March 16, some of the developments include:

  • Formed and poured footings along the lower level
  • Excavated and installed the sewer main lines
  • Began backfilling around the area facing 5th Street, which will be the main entrance
  • Construction of the elevator shaft

In addition, one of our lower level meeting rooms, the Brodhead room, will have a partition installed to pour a footing for the new building. This should be finished the first part of April.

Throughout construction, the eastern portion of 5th Street will remain closed. Patients with appointments in Family Medicine, Employee Wellness and visiting the Emergency Department will continue to use the parking and entrances on the north side of our campus; entering from 4th Street. All other patients will park south and west of the hospital building and enter through the hospital entrance, which faces 5th Street. Need additional entrance or parking information? See the links below.

Parking & Entrance Map

Driving and Entrance Directions (English)

Driving and Entrance Directions (Spanish)

Visit us on  FACEBOOK for recent construction progress photos and drone footage.